A federal judge in Washington ruled on Saturday, Nov. 14, that the Trump administration cannot close East Potomac Park and its public golf course on Sunday as planned, CBS News reports. U.S. District Judge Ana Reyes sided with a D.C. preservation group and two local golfers who argued the closure is a step toward replacing the course with a new design by architect Tom Fazio.
Her order lasts until Nov. 28. It stops the closure but does not make the government actively manage the park or the course, according to CBS. Reyes also called the administration’s justifications for the closure pretextual and wrote that the government “reverse-engineers additional justifications” for the park’s closure, per CBS.
The ruling is the latest in a case that has run since February and has turned from a dispute about a golf course into a dispute about what the administration told the court. Below is how it got here and what the dates ahead look like.
How did a golf course case get this heated?
| Date | What happened |
|---|---|
| February 2026 | Preservation advocates and golfers file suit, per NPR |
| October | The National Park Service cuts down more than 500 trees at the course in a weekend, per CBS |
| Oct. 26 | Reyes extends her ban on tree removal and requires 10 days’ written notice before any closure or irreversible change; the government appeals, per NPR |
| Oct. 28 | Government lawyers acknowledge in a filing that there is a plan to close the park in mid-November, per NPR |
| Oct. 30 | Reyes opens an inquiry into whether officials misled the court, per NPR |
| Nov. 13 | Hearing on the closure, where she presses the government on why the closure could not wait, per CBS |
| Nov. 14 | Reyes blocks the Nov. 15 closure through Nov. 28 |
NPR reported on Oct. 30 that Justice Department lawyers had said for months in filings and hearings that no final plan existed, even as President Trump posted about one on social media. At Friday’s hearing, according to CBS, Associate Attorney General Stanley Woodward said he would be surprised to learn there is a contract with Fazio or any affiliated company finalizing the new course plans.
What does the government say, and what are the numbers?
The administration gave three reasons for closing the whole park: a deteriorating sea wall, safety risks at the course, and the fact that the National Links Trust would stop operating the course on Nov. 15. Reyes asked why, if the situation was so urgent, the park was not closed immediately, noting that thousands of runners went through it for the Marine Corps Marathon last month, according to CBS.
Justice Department lawyer Adam Gustafson told the court that “when the president talks, the agencies listen,” CBS reports. He also argued that a closure would not mean construction starts right away, because the Park Service still has environmental and historic-preservation reviews to finish.
The Park Service has said there is no plan yet to repair the sea wall. A proposal it sent to the Commission of Fine Arts puts a new sea wall at more than $300 million and at least two and a half years of work. By our math that is at least 30 months, double the roughly 15 months CBS says is expected before the new course opens. The administration also said in a notice published Friday that it will solicit a contract for work on 20,700 linear feet of sea wall infrastructure, which is about 3.9 miles.
The National Capital Planning Commission is set to consider the new course design on Dec. 3, five days after Reyes’s order expires. Reyes has also opened an inquiry into whether officials from Interior, Justice and the Park Service misrepresented facts to her.